THE PROJECT

Site package supporting a 62,000 SF multi-phase facility expansion for PerkinElmer, totaling over $1.5 million.

  • Parking area grading and construction

  • Two drainage ponds

  • Sewer pump station installation

  • Temporary sewer relocation

  • Stairs and generator pad flatwork

  • Retaining walls

  • Front access rework

  • Interior pit excavation around columns

HOPKINGTON

Personalized Health Innovation

Center of Excellence – PerkinElmer

THE RESULT

A fully reconfigured campus exterior — new parking, drainage ponds, upgraded front entry, and all flatwork and retaining structures needed to support the expanded facility.