BRIDGEWATER
F.W. Webb – Bridgewater Branch
THE PROJECT
Full site package for F.W. Webb's new Bridgewater branch location, with our contract exceeding $4.5 million.
Excavation of building foundation footprint (1,385 linear feet)
Extensive cuts and fills
Cultec chamber and drainage system installation
Light pole bases and guard rails
Binder course pavement (2.5" — approx. 29,300 sq. yds.)
Wear course pavement (1.5" — approx. 30,250 sq. yds.)
THE RESULT
A complete, fully paved commercial site — over 59,000 square yards of pavement installed with a functioning drainage system and all site infrastructure in place.